Agenda and minutes
Resources and Governance Scrutiny Committee - Thursday, 18th July, 2024 10.00 am
Venue: Council Antechamber, Level 2, Town Hall Extension. View directions
Contact: Charlotte Lynch
Media
No. | Item |
---|---|
Update on Progress for Aviva Studios PDF 169 KB Report of the Deputy Chief Executive and the Strategic Director (Growth and Development).
This report provides an update on the delivery of Aviva Studios – home of Factory International, including completion of the construction programme and working with Factory International on the ongoing management and performance of the venue. Minutes: The committee considered a report of the Deputy Chief Executive and the Strategic Director (Growth and Development) which provided an update on the delivery of Aviva Studios – home of Factory International – including completion of the construction programme and the ongoing management and performance of the venue.
Key points and themes within the report included:
Some of the key points and queries that arose from the committee’s discussion included:
The Director of Capital Programmes introduced the report and stated that the construction of the project was a significant milestone achieved since the last update to the committee and that work was currently ongoing to resolve initial snagging and defects, which he stated was normal in any construction project. He highlighted the social value benefits of the work and stated that fundraising had been positive to date and would continue. Members were advised that, although not finished, officers remained confident that the project would be within the revised budget. He stated that the Council continued to be represented on Factory International’s board and that future reporting on the organisation’s performance and the business plan would be to Economy and Regeneration Scrutiny Committee.
The Deputy Leader stated that the opening of Aviva Studios had a big impact on Manchester and would attract national investment. He acknowledged that there would be lessons learned from the project but emphasised that the scale of the project should not be underestimated as this was unique to the country and had been recognised internationally.
In response to members’ concern regarding future reporting to Economy and Regeneration Scrutiny Committee, as opposed to this committee, the Deputy Leader explained that this was because Aviva Studios fell under the remit of culture, which was reported to Economy and Regeneration Scrutiny Committee, but it was agreed that a report would be provided to this ... view the full minutes text for item 49. |
|
Annual S106 Monitoring Report PDF 316 KB Report of the Strategic Director (Growth and Development).
The report provides an update to the Committee on the Council’s Section 106 (s106) activity for 2023/24 and to date. Additional documents: Minutes: The committee considered a report of the Strategic Director (Growth and Development) which provided an update on the Council’s Section 106 (s106) activity for 2023/24 and to date.
Key points and themes within the report included:
Some of the key points and queries that arose from the committee’s discussion included:
The Executive Member for Housing and Development introduced the report and highlighted that s106 agreements formed part of the planning process to ensure investment in communities, such as affordable housing; tree planting; or sport and leisure provision. He highlighted that 92% of affordable housing was delivered through the imposition of planning conditions, as opposed to the s106 process, and that the Planning and Infrastructure Bill had been tabled by the new government. This would include changes to the s106 process, and the Council was beginning to look into the impact of this.
In response to queries, the Executive Member for Housing and Development welcomed the government’s commitment to delivering more affordable housing. He stated that the Council shared this aim and was preparing to deliver more affordable housing with stakeholders and partners. He commented that the Council would welcome more funding to increase the number of planning officers available to process applications. The Strategic Director (Growth and Development) also highlighted the need for additional capacity in statutory organisations such as the Environment Agency and the Council was lobbying the government to take this into consideration.
The Assistant Director of Planning and Building Control explained that where an s106 obligation was marked as pending, this meant that the agreement was awaiting signature and he hoped delays in signing agreements would be addressed by the Planning and ... view the full minutes text for item 50. |
|
Review of Development Agreements PDF 101 KB Report of the Director of Development.
This report provides an update on the processes regarding development agreements, monitoring arrangements and overages pertaining to new development across the city on Council land and assets. An outline is provided on the governance arrangements along with how agreements are negotiated, managed, and monitored.
Minutes: The committee considered a report of the Director of Development which provided an update on the processes regarding development agreements, monitoring arrangements and overages pertaining to new development on council land and assets across the city.
Key points and themes within the report included:
Some of the key points and queries that arose from the committee’s discussion included:
In response to a query about due diligence, the Head of Commercial Governance explained that a thorough and robust due diligence process was taken on a number of key transactions and the same principles were applied to assess the organisations that the Council entered into contractual arrangements with regarding development agreements. She stated that the Council’s Due Diligence Framework was utilised throughout the life of a transaction to ensure that officers were aware of any changes to the entity which the Council has an arrangement with. Members were advised that activity had been commissioned and undertaken by Ernst & Young to inform the Council’s continual improvement process around development agreements and some wider governance points arose from this, which were highlighted in the report. Many of Ernst & Young’s recommendations were bespoke to Manchester although it was stated that some had been implemented in other local authorities.
The Director of Development explained that Heads of Terms outlined the commercial variables, roles, responsibilities and outputs of development investment activity and the negotiation of these was fluid until finalised, at which point consultation with ward members was appropriate. He stated that the translation of Heads of Terms into a commercial arrangement, governance and required consultation was well exemplified by the Wythenshawe Joint Venture.
The Strategic Director (Growth and Development) highlighted what could be included in Heads of Terms, such as a land values transaction, development management fees and long stop dates.
In response to a query regarding reputational considerations, the Head of Commercial Governance provided assurances that these were taken into account through a pre-transaction due diligence process. She agreed to share further detail on this process with members of the committee.
Decision:
To note the report. |
|
Progress update on the development of the Our Manchester Strategy 2025-2035 PDF 968 KB Report of the Assistant Chief Executive.
This report provides an update on the development of a new Our Manchester Strategy 2025-2035. A project team and steering group was formed in late 2023 ahead of the phase 1 engagement being launched in early 2024. This report provides a summary of the approach to engagement, the overall phase 1 engagement reach and a summary of the findings that are most relevant to the work of the committee. Additional documents:
Minutes: The Committee considered the report of the Assistant Chief Executive that provided an update on the development of a new Our Manchester Strategy 2025-2035. A project team and steering group was formed in late 2023 ahead of the phase 1 engagement being launched in early 2024. This report provides a summary of the approach to engagement, the overall phase 1 engagement reach and a summary of the findings that are most relevant to the work of the Committee.
Key points and themes in the report included:
· Providing an introduction and background, describing that the Our Manchester Strategy 2025 was the ten-year strategy for the city and the current Our Manchester Strategy was due to expire in 2025; · Officers had completed the first phase of development for the next Our Manchester Strategy for 2025 to 2035; and · Providing an update on the activity undertaken to date, a summary of the outputs from the first phase of the development for the new strategy, and a summary of the next steps.
Some of the key points that arose from the Committee’s discussions were:
· Why specific wording had been chosen for survey questions, particularly the question ‘What makes you proud of Manchester?’; · Noting that flytipping was a concern to respondents, and querying what impact this would have on the new Strategy; · The cost of the engagement exercise; · Engagement with businesses; and · How staff would be involved in the development of the new Strategy.
The Assistant Chief Executive introduced the report and provided a brief overview of the work to date on the development of the new Our Manchester Strategy. He stated that the first phase of the engagement focused on maximising the number of people having a say on the future of the city and ensuring diverse responses. He explained that this had resulted in an extensive engagement exercise with over 10,000 responses through a survey, in-person engagement and consultation with VCSE organisations and partnership boards and groups. He advised that emerging themes indicated a pride across the city for the people, character, diversity and community spirit of Manchester and that public transport, green spaces, cleanliness of the city and safety were areas which respondents suggested could be improved. He also stated that an extensive Equality Impact Assessment process had been undertaken and this enabled engagement to be targeted in difficult-to-reach areas.
In response to the Chair’s query regarding the wording of questions, the Assistant Chief Executive stated that the purpose of the Strategy was to be ambitious and visionary and intended to look ahead to the future.
The Assistant Chief Executive recognised that the cleanliness of the city was identified as a key priority for respondents in the survey and he expected this to feature in the priorities of the new Strategy. He stated that the Our Manchester Strategy was the overall strategy for the city, which would inform other strategies and policies, and Place Plans would be developed and were likely to include cleanliness as a key theme alongside other local factors ... view the full minutes text for item 52. |
|
Report of the Governance and Scrutiny Support Unit.
This report provides the Committee with details of key decisions that fall within the Committee’s remit and an update on actions resulting from the Committee’s recommendations. The report also includes the Committee’s work programme, which the Committee is asked to amend as appropriate and agree. Minutes: The committee received a report of the Governance and Scrutiny Support Unit which provided details of key decisions that fell within the Committee’s remit and any items for information previously requested by the Committee. Members noted that a private work programming session would take place following the conclusion of the meeting.
The Chair reminded members that a tour of the Town Hall would be taking place before the next meeting. A member requested that a capital budget update on the Our Town Hall project be provided to members in advance of the committee meeting, which the City Treasurer agreed to share.
The Chair also noted a significant number of items listed on the committee’s work programme for October and stated that he would be discussing with officers whether any of these reports could be deferred to a later meeting.
Decision: That the report be noted. |
|
Our New Finance & HR System - PART A PDF 108 KB Report of the City Treasurer and the Director of HROD and Transformation.
This report provides an update on the work undertaken to replace the Council’s legacy SAP HR and Finance system (also referred to as an Enterprise Resource Planning (ERP) system) since a previous report on 7 March 2024, including an update on the current contractual position and immediate next steps. Minutes: The committee considered a report of the City Treasurer and the Director of HROD and Transformation which provided an update on the work undertaken to replace the Council’s legacy SAP HR and finance system since the last update to the committee in March.
Key points and themes within the report included:
The City Treasurer introduced the report and stated that preferred bidders had been selected at the time of the last update to the committee in March but this could not be announced at the time due to a standstill period being underway. He advised the committee that S/4Hana was the preferred supplier for the finance system and Success Factors for HR and that, whilst the platform would continue to be SAP, it would be a different system to that currently in use. He highlighted that the current SAP system was a legacy product which had been in use at the Council since 2006.
The City Treasurer also advised that the ‘go live’ date for the finance system had been delayed to 1 April 2026 as a result of the procurement process and contractual negotiations taking longer than initially anticipated. He explained that the board, implementation partners and external auditors advised that launching at the end of a financial year was more desirable. It was confirmed that HR and payroll modules would be phased in throughout 2025.
Decision:
To note the part A report. |
|
Exclusion of Press and Public The officers consider that the following item contains exempt information as provided for in the Local Government Access to Information Act and that the public interest in maintaining the exemption outweighs the public interest in disclosing the information. The Committee is recommended to agree the necessary resolutions excluding the public from the meeting during consideration of this item. Minutes: Decision:
That the press and public be excluded during consideration of the following item which involved consideration of exempt information relating to the financial or business affairs of particular persons and the public interest in maintaining the exemption outweighed the public interest in disclosing the information.
|
|
Our New Finance & HR System - PART B Report of the City Treasurer and the Director of HROD and Transformation.
This report provides an update on the work undertaken to replace the Council’s legacy SAP HR and Finance system (also referred to as an Enterprise Resource Planning (ERP) system) since a previous report on 7 March 2024, including an update on the current contractual position and immediate next steps. Minutes: The committee considered a confidential report of the City Treasurer and the Director of HROD and Transformation which provided further detail to item 9.
The committee’s discussion centred around how staff would be trained to use the new system; the purpose of the discovery phase; seeking clarification on the technical language and jargon in the report; and if there were any implications on hardware as a result of the project.
The committee wished officers luck with the implementation of the new finance and HR system.
Decision:
To note the part B report.
|