Decision details

Decision details

Piccadilly Area Phase 1 (2020/02/28B)

Decision Maker: City Treasurer

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

The approval of capital expenditure from Sustaining  Key Initiatives budget for the appointment of a Design and Build Contractor to undertake detailed design and planning. Also early works/ enabling works within Piccadilly area.

Decision:

The Deputy Chief Executive and City Treasurer approves capital expenditure of £1,811,000 from the Sustaining Key Initiatives budget for the appointment of a Contractor to undertake works to Piccadilly Area Phase 1.

 

This work will include the demolition of the free standing wall and other early works/enabling works within Piccadilly area, to create a safer environment and facilitate longer term improvements.

Publication date: 30/04/2020

Date of decision: 30/04/2020

Effective from: 08/05/2020

Accompanying Documents: