A57 Hyde Road Pinch Point. 2019/04/25E

To remove a pinch point in traffic flow on the A57 Hyde Road, where the carriageway is reduced in width from 2 lanes in either direction to one lane where it runs under a disused railway bridge.  The project will see the width of the carriageway increased  to accommodate two lanes of traffic flow in both directions, future provision for cyclists and a new bridge to carry the footpath that runs along the disused railway line.

 

To enable the scheme to be delivered 4 pieces of land are required.  Negotiations have been successful with 3 of the landowners but it has become necessary to start a CPO for the final piece of land.

 

Decision type: Key

Reason Key: Affects more than 1 ward;

Decision status: Recommendations Approved

Notice of proposed decision first published: 25/04/2019

Decision due: May 2019 by Chief Executive

Department: Chief Executives

Contact: Nichola McHale, Programme Manager Email: n.mchale@manchester.gov.uk Email: nichola.mchale@manchester.gov.uk.

Documents

  • Delegated Approvals Report